Glen Rock Front Porch Build
MediumIn ProgressAug 31, 2026 – Sep 22, 2026 (23 days)· Hannah Vogel· 5 Rock Rd, Glen Rock, NJ
Project
Client
Start date (from tasks)
End date (from tasks)
Priority
Job site
Description
0% complete · 0/6 tasks
Task List
Manage task hierarchy, dates and dependencies
| WBS | Task Name | Duration | Predecessors | Type | Status | Start | End | Action |
|---|---|---|---|---|---|---|---|---|
| 1 | Footings & piers Concrete Crew · Miguel Alvarez · 7:00 AM–3:30 PM | 3 Days | -- | Task | Aug 31, 2026 | Sep 02, 2026 | ||
| 2 | Porch deck framing Deck Crew · Ila Wagner · 7:00 AM–3:30 PM | 3 Days | 1 | Task | Sep 04, 2026 | Sep 06, 2026 | ||
| 3 | Column & beam set Framing Crew · Peter Carpenter · 7:00 AM–3:30 PM | 2 Days | 2 | Task | Sep 09, 2026 | Sep 10, 2026 | ||
| 4 | Porch roof & metal panels Framing Crew · Unassigned · 7:00 AM–3:30 PM | 4 Days | 3 | Task | Sep 11, 2026 | Sep 14, 2026 | ||
| 5 | Railing & trim Finish Crew · Dana Ruiz · 7:00 AM–3:30 PM | 3 Days | 4 | Task | Sep 17, 2026 | Sep 19, 2026 | ||
| 6 | Milestone: Client walkthrough Design Team · Sam Scott · 11:00 AM–12:00 PM | 1 Days | 5 | Milestone | Sep 22, 2026 | Sep 22, 2026 |
Timeline
Aug 3123 daysSep 22
1. Footings & piers
2. Porch deck framing
3. Column & beam set
4. Porch roof & metal panels
5. Railing & trim
6. Client walkthrough
Activity
Schedule created
Dave Reyes · Aug 01, 2026, 2:00 PM