Schedule

Fair Lawn Roof & Soffit

CriticalIn ProgressAug 27, 2026Sep 11, 2026 (16 days)· Dominic Castellano· 301 Fair Lawn Ave, Fair Lawn, NJ
Project
Client
Start date (from tasks)
End date (from tasks)
Priority
Job site
Description
17% complete · 1/6 tasks

Task List

Manage task hierarchy, dates and dependencies

WBSTask NameDurationPredecessorsTypeStatusStartEndAction
1
Dumpster drop
Framing Crew · Bob Tech · 6:30 AM8:00 AM
1 Days--DeliveryAug 27, 2026Aug 27, 2026
2
Tear-off
Framing Crew · Lacota Dunlap · 6:30 AM4:30 PM
2 Days--TaskAug 28, 2026Aug 29, 2026
3
Re-sheath & underlayment
Framing Crew · Kevin Doyle · 7:00 AM3:30 PM
2 Days2TaskSep 01, 2026Sep 02, 2026
4
Soffit & fascia
Finish Crew · Khoa Huynh · 7:00 AM3:30 PM
3 Days3TaskSep 03, 2026Sep 05, 2026
5
Gutter install
Deck Crew · Unassigned · 7:00 AM3:30 PM
2 Days4TaskSep 08, 2026Sep 09, 2026
6
Roof final inspection
Design Team · Marissa Kohl · 1:00 PM2:30 PM
1 Days5InspectionSep 11, 2026Sep 11, 2026

Timeline

Aug 2716 daysSep 11
1. Dumpster drop
2. Tear-off
3. Re-sheath & underlayment
4. Soffit & fascia
5. Gutter install
6. Roof final inspection

Activity

  • Schedule created

    Dave Reyes · Aug 01, 2026, 2:00 PM