Schedule

Ridgewood Basement Finish

HighIn ProgressAug 25, 2026Sep 21, 2026 (28 days)· Alicia Brennan· 88 Godwin Ave, Ridgewood, NJ
Project
Client
Start date (from tasks)
End date (from tasks)
Priority
Job site
Description
14% complete · 1/7 tasks

Task List

Manage task hierarchy, dates and dependencies

WBSTask NameDurationPredecessorsTypeStatusStartEndAction
1
Layout & partition framing
Framing Crew · Ila Wagner · 7:00 AM3:30 PM · Frame partition walls per approved basement layout.
3 Days--TaskAug 25, 2026Aug 27, 2026
2
Egress window cut & install
Concrete Crew · Miguel Alvarez · 7:00 AM3:30 PM
2 Days1TaskAug 28, 2026Aug 29, 2026
3
Bath rough-in coordination
Finish Crew · Kevin Doyle · 8:00 AM4:00 PM
2 Days2TaskSep 02, 2026Sep 03, 2026
4
Insulation delivery
Framing Crew · Lacota Dunlap · 7:30 AM9:30 AM
1 Days--DeliverySep 04, 2026Sep 04, 2026
5
Drywall hang
Finish Crew · Unassigned · 7:00 AM3:30 PM
4 Days4TaskSep 07, 2026Sep 10, 2026
6
Trim & doors
Finish Crew · Sloane Morgan · 7:00 AM3:30 PM
4 Days5TaskSep 14, 2026Sep 17, 2026
7
Final basement inspection
Design Team · Marissa Kohl · 9:00 AM11:00 AM
1 Days6InspectionSep 21, 2026Sep 21, 2026

Timeline

Aug 2528 daysSep 21
1. Layout & partition framing
2. Egress window cut & install
3. Bath rough-in coordination
4. Insulation delivery
5. Drywall hang
6. Trim & doors
7. Final basement inspection

Activity

  • Schedule created

    Dave Reyes · Aug 01, 2026, 2:00 PM