Ridgewood Basement Finish
HighIn ProgressAug 25, 2026 – Sep 21, 2026 (28 days)· Alicia Brennan· 88 Godwin Ave, Ridgewood, NJ
Project
Client
Start date (from tasks)
End date (from tasks)
Priority
Job site
Description
14% complete · 1/7 tasks
Task List
Manage task hierarchy, dates and dependencies
| WBS | Task Name | Duration | Predecessors | Type | Status | Start | End | Action |
|---|---|---|---|---|---|---|---|---|
| 1 | Layout & partition framing Framing Crew · Ila Wagner · 7:00 AM–3:30 PM · Frame partition walls per approved basement layout. | 3 Days | -- | Task | Aug 25, 2026 | Aug 27, 2026 | ||
| 2 | Egress window cut & install Concrete Crew · Miguel Alvarez · 7:00 AM–3:30 PM | 2 Days | 1 | Task | Aug 28, 2026 | Aug 29, 2026 | ||
| 3 | Bath rough-in coordination Finish Crew · Kevin Doyle · 8:00 AM–4:00 PM | 2 Days | 2 | Task | Sep 02, 2026 | Sep 03, 2026 | ||
| 4 | Insulation delivery Framing Crew · Lacota Dunlap · 7:30 AM–9:30 AM | 1 Days | -- | Delivery | Sep 04, 2026 | Sep 04, 2026 | ||
| 5 | Drywall hang Finish Crew · Unassigned · 7:00 AM–3:30 PM | 4 Days | 4 | Task | Sep 07, 2026 | Sep 10, 2026 | ||
| 6 | Trim & doors Finish Crew · Sloane Morgan · 7:00 AM–3:30 PM | 4 Days | 5 | Task | Sep 14, 2026 | Sep 17, 2026 | ||
| 7 | Final basement inspection Design Team · Marissa Kohl · 9:00 AM–11:00 AM | 1 Days | 6 | Inspection | Sep 21, 2026 | Sep 21, 2026 |
Timeline
Aug 2528 daysSep 21
1. Layout & partition framing
2. Egress window cut & install
3. Bath rough-in coordination
4. Insulation delivery
5. Drywall hang
6. Trim & doors
7. Final basement inspection
Activity
Schedule created
Dave Reyes · Aug 01, 2026, 2:00 PM