Maplewood Kitchen Remodel
MediumBlockedAug 20, 2026 – Sep 17, 2026 (29 days)· Shaun Scott· 7 Maplewood Ave, Glen Rock, NJ
Project
Client
Start date (from tasks)
End date (from tasks)
Priority
Job site
Description
25% complete · 1/4 tasks
Task List
Manage task hierarchy, dates and dependencies
| WBS | Task Name | Duration | Predecessors | Type | Status | Start | End | Action |
|---|---|---|---|---|---|---|---|---|
| 1 | Milestone: Design sign-off Design Team · Sam Scott · 9:00 AM–10:00 AM | 1 Days | -- | Milestone | Aug 20, 2026 | Aug 20, 2026 | ||
| 2 | Cabinet order lead time Design Team · Marissa Kohl · 7:00 AM–3:30 PM · Vendor lead time — no field work during this window. | 14 Days | 1 | Task | Aug 21, 2026 | Sep 03, 2026 | ||
| 3 | Demolition Finish Crew · Unassigned · 7:00 AM–3:30 PM | 2 Days | 2 | Task | Sep 08, 2026 | Sep 09, 2026 | ||
| 4 | Cabinet install Finish Crew · Lena Ortiz · 7:00 AM–3:30 PM · Blocked pending cabinet delivery confirmation. | 4 Days | 3 | Task | Sep 14, 2026 | Sep 17, 2026 |
Timeline
Aug 2029 daysSep 17
1. Design sign-off
2. Cabinet order lead time
3. Demolition
4. Cabinet install
Activity
Schedule created
Dave Reyes · Aug 01, 2026, 2:00 PM