Cedar Point Lot 4 Addition
CriticalIn ProgressAug 27, 2026 – Sep 11, 2026 (16 days)· Nhat Min Hoo· 18 Cedar Point Dr, Paramus, NJ
Project
Client
Start date (from tasks)
End date (from tasks)
Priority
Job site
Description
25% complete · 1/4 tasks
Task List
Manage task hierarchy, dates and dependencies
| WBS | Task Name | Duration | Predecessors | Type | Status | Start | End | Action |
|---|---|---|---|---|---|---|---|---|
| 1 | Foundation pour Concrete Crew · Ray Delgado · 7:00 AM–3:30 PM | 3 Days | -- | Task | Aug 27, 2026 | Aug 29, 2026 | ||
| 2 | Framing package delivery Framing Crew · Marcus Hale · 8:00 AM–10:00 AM | 1 Days | 1 | Delivery | Sep 02, 2026 | Sep 02, 2026 | ||
| 3 | Wall & roof framing Framing Crew · Unassigned · 7:00 AM–3:30 PM | 6 Days | 2 | Task | Sep 03, 2026 | Sep 08, 2026 | ||
| 4 | Rough framing inspection Design Team · Marissa Kohl · 1:00 PM–3:00 PM | 1 Days | 3 | Inspection | Sep 11, 2026 | Sep 11, 2026 |
Timeline
Aug 2716 daysSep 11
1. Foundation pour
2. Framing package delivery
3. Wall & roof framing
4. Rough framing inspection
Activity
Schedule created
Dave Reyes · Aug 01, 2026, 2:00 PM