Schedule

Cedar Point Lot 4 Addition

CriticalIn ProgressAug 27, 2026Sep 11, 2026 (16 days)· Nhat Min Hoo· 18 Cedar Point Dr, Paramus, NJ
Project
Client
Start date (from tasks)
End date (from tasks)
Priority
Job site
Description
25% complete · 1/4 tasks

Task List

Manage task hierarchy, dates and dependencies

WBSTask NameDurationPredecessorsTypeStatusStartEndAction
1
Foundation pour
Concrete Crew · Ray Delgado · 7:00 AM3:30 PM
3 Days--TaskAug 27, 2026Aug 29, 2026
2
Framing package delivery
Framing Crew · Marcus Hale · 8:00 AM10:00 AM
1 Days1DeliverySep 02, 2026Sep 02, 2026
3
Wall & roof framing
Framing Crew · Unassigned · 7:00 AM3:30 PM
6 Days2TaskSep 03, 2026Sep 08, 2026
4
Rough framing inspection
Design Team · Marissa Kohl · 1:00 PM3:00 PM
1 Days3InspectionSep 11, 2026Sep 11, 2026

Timeline

Aug 2716 daysSep 11
1. Foundation pour
2. Framing package delivery
3. Wall & roof framing
4. Rough framing inspection

Activity

  • Schedule created

    Dave Reyes · Aug 01, 2026, 2:00 PM