Harbor Ridge Rear Deck
HighIn ProgressAug 24, 2026 – Sep 11, 2026 (19 days)· Lionel Will· 42 Harbor Ridge Rd, Ridgewood, NJ
Project
Client
Start date (from tasks)
End date (from tasks)
Priority
Job site
Description
17% complete · 1/6 tasks
Task List
Manage task hierarchy, dates and dependencies
| WBS | Task Name | Duration | Predecessors | Type | Status | Start | End | Action |
|---|---|---|---|---|---|---|---|---|
| 1 | Site prep & demo Deck Crew · Dave Reyes · 7:00 AM–3:30 PM · Remove existing deck boards, haul debris. | 2 Days | -- | Task | Aug 24, 2026 | Aug 25, 2026 | ||
| 2 | Footing excavation Concrete Crew · Ray Delgado · 7:00 AM–3:30 PM · Dig and pour 9 sonotube footings to 36in frost depth. | 2 Days | 1 | Task | Aug 26, 2026 | Aug 27, 2026 | ||
| 3 | Township footing inspection Design Team · Marissa Kohl · 9:00 AM–11:00 AM · Ridgewood building dept inspection window. | 1 Days | 2 | Inspection | Aug 31, 2026 | Aug 31, 2026 | ||
| 4 | Deck framing Framing Crew · Marcus Hale · 7:00 AM–3:30 PM · Set beams, joists and ledger with flashing. | 4 Days | 3 | Task | Sep 01, 2026 | Sep 04, 2026 | ||
| 5 | Composite decking install Deck Crew · Unassigned · 7:00 AM–3:30 PM | 3 Days | 4 | Task | Sep 07, 2026 | Sep 09, 2026 | ||
| 6 | Milestone: Client walkthrough Design Team · Sam Scott · 10:00 AM–11:30 AM | 1 Days | 5 | Milestone | Sep 11, 2026 | Sep 11, 2026 |
Timeline
Aug 2419 daysSep 11
1. Site prep & demo
2. Footing excavation
3. Township footing inspection
4. Deck framing
5. Composite decking install
6. Client walkthrough
Activity
Schedule created
Dave Reyes · Aug 01, 2026, 2:00 PM